Archive of: Construction Articles

Issue

Title

Construction steady so far June Issue 4 2015

Construction steady so far

April Issue 1 2015

Soldotna tentatively scheduled for road upgrades in 2016

UAF plant estimate $50M over budget March Issue 5 2015

UAF plant estimate $50M over budget

The University of Alaska Fairbanks will likely have to wait a year longer to get its new heat and power plant up and running.

Long-awaited Sealaska land transfer completed March Issue 3 2015

Long-awaited Sealaska land transfer completed

It took 43 years, two months and 17 days since the passage of the Alaska Native Claims Settlement Act, but Sealaska Corp. is finally whole.